TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/RAIL/116402/2020              (ii). Name of Project for which Forest Land is required : WDFC (ROB 6-PCL)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : DFC Line is crossing Chadotar-Gadh road near Palanpur city for this purpose, ROB (6-PCL) is proposed on the same alignment of road. DFCC is targeted project and being monitored by PMO.              (iv). File no. : 6-GJB058/2021-BHO              (v). State : Gujarat              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.308
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/GJ/RAIL/116402/202021/12/2020aa22/12/2020   08/03/2021 Banaskantha SF :16/03/2021Mehsana SF Circle:
  18/03/2021 (Banaskantha SF)

Gujarat:
03/04/2021
Gujarat:
08/04/2021
Gandhinagar:
17/05/2021
08/06/2021
By :Regional Office
Gujarat
06/12/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Gandhinagar) on:20/12/2021  
Query raised by State Government (Gujarat) on:31/01/2022  
Query raised by Nodal Officer on:04/07/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .