TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/Pipeline/154942/2022              (ii). Name of Project for which Forest Land is required : 8” Dia Steel Gas Pipeline Connectivity From Maruti Nandan CNG Station to Kanubhai Rabari SGL CNG Station & For Bilasiya Bus Stand To Kanubhai Rabari CNG Station, Dehgam Ta:Dehgam, Dist: Gandhinagar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.47892 Ha. of Protected Forest land for laying 8” Dia Steel Gas Pipeline Connectivity From Maruti Nandan CNG Station to Kanubhai Rabari SGL CNG Station & For Bilasiya Bus Stand To Kanubhai Rabari CNG Station, Dehgam Ta:Dehgam, Dist: Gandhinagar              (iv). State : Gujarat              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.47892
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/Pipeline/154942/202227/04/2022aa29/04/2022   12/05/2022 Gandhinagar :12/05/2022Gandhinagar Circle:
  03/02/2025 (Gandhinagar)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Gandhinagar) on:25/05/2022  
Replied by UA on :10/12/2022  
Query raised by DFO (Gandhinagar) on:13/12/2022  
Replied by UA on :21/03/2023  
Query raised by DFO (Gandhinagar) on:06/04/2023  
Replied by UA on :26/05/2023  
Query raised by DFO (Gandhinagar) on:06/06/2023  
Replied by UA on :31/01/2024  
Query raised by DFO (Gandhinagar) on:20/03/2024  
Replied by UA on :27/06/2024  
Query raised by DFO (Gandhinagar) on:06/11/2024  
Replied by UA on :16/12/2024  
NOTE:- Proposal is pending at CF .
Close(X)