TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/Pipeline/147880/2021              (ii). Name of Project for which Forest Land is required : 90mm Dia MDPE Gas Pipeline Crossing Connectivity For Unichem Fine Products, Gadhoda, District: Sabarkantha.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.0012 Ha. of Protected Forest land for laying 90mm Dia MDPE Gas Pipeline Crossing Connectivity For Unichem Fine Products, Gadhoda, District: Sabarkantha.              (iv). File no. : FED/FLP/e-file/6/2023/1894/F              (v). State : Gujarat              (vi). Category of the Project : Pipeline              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0012
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/GJ/Pipeline/147880/202130/09/2021aa30/09/2021   02/11/2021 Sabarkantha-North SF :10/11/2021Mehsana SF Circle:
  06/06/2023 (Sabarkantha-North SF)

Gujarat:
20/06/2023
Gujarat:
04/07/2023
10/08/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sabarkantha-North SF) on:10/11/2021  
Replied by UA on :05/06/2023  
NOTE:- Stage-I Approval accorded by : State Government .