Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Ahmedabad SF Circle)
|
06/01/2016
|
As per the letter attached herewith
|
|
2
|
CF (Ahmedabad SF Circle)
|
EDS
|
DFO (Surendranagar SF)
|
15/01/2016
|
As per the letter attached herewith
|
|
3
|
DFO (Surendranagar SF)
|
REPLY
|
CF (Ahmedabad SF Circle)
|
07/05/2016
|
Sir,
i have solved quary for a head office letter No: JMN/29-A/B/1939-41/ Dt.01-08-2015
|
|
4
|
CF (Ahmedabad SF Circle)
|
REPLY
|
Nodal Officer
|
07/05/2016
|
Sir, DFO have solved quary for a Your office letter No: JMN/29-A/B/1939-41/ Dt.01-08-2015
|
|
5
|
Nodal Officer
|
EDS
|
CF (Ahmedabad SF Circle)
|
19/05/2016
|
As per the letter attached herewith
|
|
6
|
CF (Ahmedabad SF Circle)
|
EDS
|
DFO (Surendranagar SF)
|
21/05/2016
|
As per the letter attached herewith
|
|
7
|
DFO (Surendranagar SF)
|
REPLY
|
CF (Ahmedabad SF Circle)
|
15/10/2016
|
Sir,
(1)C.A. Scheme is Not Required for this proposal As Per Add. Pri CCF Letter No.FCA/29-A/1062-1135/dt.10/03/2016
(2)I have Give a In Principal Approval for This Proposal Our office Letter No. B/FCA/492-95/ Dt.21-05-2016 As per Add. Pri CCF Letter No.Jmn/29-A/B/1690-1760/dt.20/05/2016
(3)I have Submitted Four Copies of files to further Process As Per Forest and Environment Department Letter no: JMN/1016/1970/15/SF-38/F dt.15-09-2016
|
|
8
|
CF (Ahmedabad SF Circle)
|
REPLY
|
Nodal Officer
|
21/10/2016
|
Sir, (1)C.A. Scheme is Not Required for this proposal As Per Add. Pri CCF Letter No.FCA/29-A/1062-1135/dt.10/03/2016 (2)I have Give a In Principal Approval for This Proposal DCF office Letter No. B/FCA/492-95/ Dt.21-05-2016 As per Add. Pri CCF Letter No.Jmn/29-A/B/1690-1760/dt.20/05/2016 (3)I have Submitted Four Copies of files to further Process As Per Forest and Environment Department Letter no: JMN/1016/1970/15/SF-38/F dt.15-09-2016
|
|