A. General Details
  (i). Proposal No. : FP/GJ/Others/44095/2020              (ii). Name of Project for which Forest Land is required : 11 kv electric line for sakarben hira khant              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : for electrification of 11 kv overhead electric line of shree. sakarben hirabhai khant, 0.3045 ha total land is required for diversion              (iv). File no. : FCA-1020/3-21/20/SF-236/F              (v). State : Gujarat              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.154
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/GJ/Others/44095/202022/01/202022/01/2020   16/06/2020   22/06/2020   16/09/2020 Gir-West WL :17/09/2020Junagadh WL Circle:
  24/09/2020 (Gir-West WL)

Gujarat:
15/10/2020
Gujarat:
03/12/2020
01/01/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .