A. General Details
  (i). Proposal No. : FP/GJ/Others/34592/2018              (ii). Name of Project for which Forest Land is required : Diversion of 38.8633 Ha of forest land at village : Hazira, Taluka : Choryasi, District : Surat of Gujarat State for Expansion of RIL Hazira Manufacturing Division & Associated Facilities like Tank Farm, Warehousing, etc.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Reliance Industries Limited is seeking Diversion of approx. 38.8633 Ha of forest land at village: Hazira, Taluka: Choryasi, District : Surat for Expansion of RIL Hazira Manufacturing Division & Associated Facilities like Tank Farm, Warehousing, etc.              (iv). State : Gujarat              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 38.8633
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/Others/34592/201802/10/201809/10/2018   19/10/2018   01/12/2018   01/12/2018 Surat :01/12/2018Surat Circle:
  30/03/2021 (Surat)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Surat Circle) on:03/04/2021  
Replied by DFO (Surat) on:23/07/2021  
Query raised by Circle (Surat Circle) on:27/07/2021  
Replied by DFO (Surat) on:27/07/2021  
Query raised by Circle (Surat Circle) on:27/07/2021  
Replied by DFO (Surat) on:13/03/2024  
Query raised by Circle (Surat Circle) on:06/05/2024  
Replied by DFO (Surat) on:29/05/2024  
Query raised by Circle (Surat Circle) on:15/07/2024  
Replied by DFO () on:  
Query raised by DFO (Surat) on:28/04/2020  
Replied by UA on :18/12/2020  
Query raised by DFO (Surat) on:19/12/2020  
Replied by UA on :24/12/2020  
Query raised by DFO (Surat) on:11/02/2021  
Replied by UA on :25/02/2021  
Query raised by DFO (Surat) on:14/09/2021  
Replied by UA on :30/01/2024  
Query raised by DFO (Surat) on:08/05/2024  
Replied by UA on :13/05/2024  
Query raised by DFO (Surat) on:19/07/2024  
Replied by UA on :13/08/2024  
Query raised by DFO (Surat) on:24/07/2025  
Replied by UA on :29/07/2025  
NOTE:- Proposal is pending at DFO due to EDS raised by CF .