TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/Others/25630/2017              (ii). Name of Project for which Forest Land is required : NATIONAL OPTICAL FIBER NETWORK              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : UNDER THE NATIONAL OPTICAL FIBER NETWORK (NOFN)PROJECT OF GOVT OF INDIA, RAILTEL CORPORATION OF INDIA LTD(RCIL)IMPLEMENTING THE PHASE 1 OF THE PROJECT IN GUJARAT STATE TO CONNECT 5315 GRAM PANCHAYATS OF 11 DISTRICTS OF GUJAAT, BY LAYING APPROX 1007KMS OF OPTICAL FIBER NETWORK.              (iv). File no. : C/FCA/T-8/594-97/2016-17              (v). State : Gujarat              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.51066
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/Others/25630/201712/04/2017aa26/04/2017   05/07/2017 Sabarkantha :19/07/2017Gandhinagar Circle:
  25/01/2020 (Sabarkantha)

Gujarat:
25/01/2020
Gujarat:
26/01/2020
Gandhinagar:
28/01/2020
28/01/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sabarkantha) on:18/11/2019  
Replied by UA on :25/01/2020  
NOTE:- Stage-I Approval accorded by : State Government .