TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/Others/19176/2016              (ii). Name of Project for which Forest Land is required : PVC Pipe Line For Sea Water              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Permition Of Boring near sea-shore and setting up PVC Pipe Line For Sea Water Intake For Shrimpr awn)Hatchery,(Village Kuchhadi R.F.S. No.1119/1A)(0.1080 Ha.)              (iv). File no. : 6-GJB05/2017-BHO              (v). State : Gujarat              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.108
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/GJ/Others/19176/201602/05/201607/06/2016  21/05/2016  09/05/2016  04/05/2016   07/06/2016  07/06/2016  17/05/2016  05/05/2016   07/06/2016   18/06/2016 Porbandar :23/06/2016Junagadh Circle:
  09/09/2016 (Porbandar)

Gujarat:
27/09/2016
Gujarat:
23/12/2016
Gandhinagar:
08/02/2017
08/09/2017
By :Regional Office
Gujarat
12/10/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:14/03/2017  
Replied by State Government(Gujarat) on:21/07/2017  
Query raised by Regional Office (Gandhinagar) on:04/08/2017  
Replied by State Government(Gujarat) on:19/08/2017  
Query raised by State Government (Gujarat) on:04/05/2017  
Replied by Nodal Officer (Gujarat) on:29/06/2017  
Query raised by State Government (Gujarat) on:09/08/2017  
Replied by Nodal Officer (Gujarat) on:16/08/2017  
Query raised by Nodal Officer (Gujarat) on:10/10/2016  
Replied by Circle(Junagadh Circle) on:02/12/2016  
Query raised by Nodal Officer (Gujarat) on:14/12/2016  
Replied by Circle(Junagadh Circle) on:15/12/2016  
Query raised by Nodal Officer (Gujarat) on:09/05/2017  
Replied by Circle(Junagadh Circle) on:12/05/2017  
Query raised by Circle (Junagadh WL Circle) on:18/10/2016  
Replied by DFO (Porbandar) on:21/11/2016  
Query raised by Circle (Junagadh WL Circle) on:14/12/2016  
Replied by DFO (Porbandar) on:15/12/2016  
Query raised by Circle (Junagadh WL Circle) on:11/05/2017  
Replied by DFO (Porbandar) on:11/05/2017  
Query raised by DFO (Porbandar) on:18/10/2016  
Replied by UA on :25/10/2016  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Gandhinagar) on:29/12/2021  
Replied by State Government(Gujarat) on:03/03/2022  
Query raised by Regional Office (Gandhinagar) on:16/03/2022  
Replied by State Government(Gujarat) on:06/05/2022  
Query raised by Regional Office (Gandhinagar) on:06/06/2022  
Query raised by State Government (Gujarat) on:03/02/2022  
Replied by Nodal Officer (Gujarat) on:02/03/2022  
Query raised by State Government (Gujarat) on:22/03/2022  
Replied by Nodal Officer (Gujarat) on:07/04/2022  
Query raised by State Government (Gujarat) on:06/06/2022  
Query raised by Nodal Officer on:04/07/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .