Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Bharuch SF Circle)
|
EDS
|
DFO (Narmada SF)
|
27/10/2023
|
Physical files not received till today
|
|
2
|
DFO (Narmada SF)
|
REPLY
|
CF (Bharuch SF Circle)
|
02/11/2023
|
As long as the proposal is pending on the Parivesh 1.0 portal so that the proposal file is to be sent to the nodal level, the request is to be notified.
|
|
3
|
CF (Bharuch SF Circle)
|
EDS
|
DFO (Narmada SF)
|
13/12/2023
|
Physical file not received
|
|
4
|
DFO (Narmada SF)
|
EDS
|
User Agency (dgm-proj3@bharatnet.gujarat.gov.in)
|
03/04/2024
|
query1
|
|
5
|
User Agency (dgm-proj3@bharatnet.gujarat.gov.in)
|
REPLY
|
DFO (Narmada SF)
|
07/08/2024
|
The correction have been made as per the instruction received
|
|