TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/OFC/141570/2021              (ii). Name of Project for which Forest Land is required : Diversion of 1.4020 ha. Protected Forest land for the grant permission for laying Vodafone Idea Telecom Infrastructure Limited Optical Fiber Cable line in along the road of Jasdan-Navagam-Bhadli- Rojmal Road (SH) of Jasdan and Vinchchiya Taluka, Dist. Rajkot in Gujarat state.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.4020 ha. Protected Forest land for the grant permission for laying Vodafone Idea Telecom Infrastructure Limited Optical Fiber Cable line in along the road of Jasdan-Navagam-Bhadli- Rojmal Road (SH) of Jasdan and Vinchchiya Taluka, Dist. Rajkot in Gujarat state.              (iv). File no. : C/T-9/Land/149-52/2021-22              (v). State : Gujarat              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.402
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/GJ/OFC/141570/202121/04/202126/04/2021   27/04/2021   28/04/2021   21/05/2021 Rajkot SF :26/05/2021Rajkot SF Circle:
  15/07/2021 (Rajkot SF)

Gujarat:
15/07/2021
Gujarat:
19/07/2021
23/07/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Rajkot SF) on:01/06/2021  
Replied by UA on :07/07/2021  
NOTE:- Stage-I Approval accorded by : State Government .