TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/IRRIG/155759/2022              (ii). Name of Project for which Forest Land is required : Diversion of 0.2160 Ha. Reserved Forest Land for the project of the Extension of Kadana Dahod Lift Irrigation PKG-1 Underground Water Supply Pipeline, Village:-Surpura, Mota Ambaliya & Parmar na Dungarpur Ta:-Singvad, Dist:-Dahod In Gujarat State              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.2160 Ha. Reserved Forest Land for the project of the Extension of Kadana Dahod Lift Irrigation PKG-1 Underground Water Supply Pipeline, Village:-Surpura, Mota Ambaliya & Parmar na Dungarpur Ta:-Singvad, Dist:-Dahod In Gujarat State              (iv). File no. : FCA-1022-156-F              (v). State : Gujarat              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.216
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/GJ/IRRIG/155759/202224/05/202226/05/2022   29/05/2022   30/05/2022   13/06/2022 Bariya :14/06/2022Vadodara Circle:
  14/07/2022 (Bariya)

Gujarat:
25/07/2022
Gujarat:
20/08/2022
11/10/2022
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .