| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Kutch SF)
|
EDS
|
User Agency (bimalvaidya@manaksia.com)
|
14/10/2019
|
k/jmn/t-8/424-25/2019-20 dt.14.10.2019
|
|
|
2
|
User Agency (bimalvaidya@manaksia.com)
|
REPLY
|
DFO (Kutch SF)
|
27/03/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kutch Circle)
|
27/04/2021
|
As per the this office Latter dt. 26-04-2021
|
|
|
4
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
27/04/2021
|
As per apccf,land office Latter dt. 26-04-2021
|
|
|
5
|
DFO (Kutch SF)
|
EDS
|
User Agency (bimalvaidya@manaksia.com)
|
05/05/2021
|
Please compliance As per apccf,land office Latter dt. 26-04-2021
|
|
|
6
|
User Agency (bimalvaidya@manaksia.com)
|
REPLY
|
DFO (Kutch SF)
|
23/07/2021
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Kutch SF)
|
REPLY
|
CF (Kutch Circle)
|
23/07/2021
|
the correction have been made as per the instruction received
|
|
|
8
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
29/07/2021
|
as per this office letter dated 29.07/2021
|
|
|
9
|
DFO (Kutch SF)
|
EDS
|
User Agency (bimalvaidya@manaksia.com)
|
03/08/2021
|
please update your whole proposal as per the revised area
|
|
|
10
|
User Agency (bimalvaidya@manaksia.com)
|
REPLY
|
DFO (Kutch SF)
|
01/12/2021
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Kutch SF)
|
REPLY
|
CF (Kutch Circle)
|
01/12/2021
|
for the correction in demanded forest area
|
|
|
12
|
CF (Kutch Circle)
|
REPLY
|
Nodal Officer
|
01/12/2021
|
ageny want to correction in demanded forest area.
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kutch Circle)
|
27/12/2021
|
pl check revise area
|
|
|
14
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
28/12/2021
|
pl check revise area
|
|
|
15
|
DFO (Kutch SF)
|
EDS
|
User Agency (bimalvaidya@manaksia.com)
|
29/12/2021
|
please revised area
|
|
|
16
|
User Agency (bimalvaidya@manaksia.com)
|
REPLY
|
DFO (Kutch SF)
|
21/01/2022
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Kutch SF)
|
EDS
|
User Agency (bimalvaidya@manaksia.com)
|
27/01/2022
|
please correct the kml file
|
|
|
18
|
User Agency (bimalvaidya@manaksia.com)
|
REPLY
|
DFO (Kutch SF)
|
04/02/2022
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Kutch SF)
|
REPLY
|
CF (Kutch Circle)
|
05/02/2022
|
proposal submitted as per revised area
|
|
|
20
|
CF (Kutch Circle)
|
REPLY
|
Nodal Officer
|
18/02/2022
|
as per this office letter dated 17.02.2022
|
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
14/03/2023
|
EDS letter dated 13.03.2023.
|
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
24/03/2023
|
GoI Query
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (Kutch Circle)
|
27/03/2023
|
As per GoI query
|
|
|
24
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
08/04/2023
|
As per GoI query
|
|
|
25
|
DFO (Kutch SF)
|
REPLY
|
CF (Kutch Circle)
|
18/06/2024
|
reply send to ccf office with office letter no 208 Dt.18/06/2024
|
|
|
26
|
CF (Kutch Circle)
|
REPLY
|
Nodal Officer
|
19/06/2024
|
he correction have been made as per the instruction received
|
|
|
27
|
Nodal Officer
|
EDS
|
CF (Kutch Circle)
|
03/01/2026
|
Upload a copy letter of correction
|
|
|
28
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
05/01/2026
|
Upload a copy letter of correction
|
|
|
29
|
DFO (Kutch SF)
|
REPLY
|
CF (Kutch Circle)
|
23/01/2026
|
upload a copy letter of correction
|
|
|
30
|
CF (Kutch Circle)
|
EDS
|
DFO (Kutch SF)
|
02/02/2026
|
Please upload a copy letter of correction
|
|