A. General Details
  (i). Proposal No. : FP/DN/Others/17626/2016              (ii). Name of Project for which Forest Land is required : Silvasa Spurline              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.3695 Hect. Protected Forest land (Road side strip land) for laying 12” dia (30 cm) Natural Gas Pipeline from our existing pipeline near village Eklahare, Taluka Umargam, Dist. Valsad to Reliance Industry situated in Dadra & Nagar Haveli (U/T)              (iv). File no. : 7-5/3-FD/563              (v). State : Dadar & Nagar Haveli              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.3695
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/DN/Others/17626/201620/01/2016aa02/02/2016   05/02/2016   Territorial Division :05/02/2016Forest Department, Dadra & Nagar Haveli, Silvassa.:
  27/05/2016 (Territorial Division)

Dadar & Nagar Haveli:
10/06/2016
Dadar & Nagar Haveli:
19/07/2016
16/10/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .