Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
24/10/2017
|
The estimate for CA has to be reviewed. The cost norms to be similar to that of Similar Projects
|
|
2
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
EDS
|
DFO (Territorial Division)
|
24/10/2017
|
The estimate for CA has to be revised and the cost norms to be similar to that of similar projects
|
|
3
|
DFO (Territorial Division)
|
REPLY
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
01/11/2017
|
The Compensatory Afforestation Scheme was prepared to an amount of Rs. 7.86 Lakhs. The revised estimate had been uploaded online also.
|
|
4
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
REPLY
|
Nodal Officer
|
08/11/2017
|
The revised CA is uploaded
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
05/12/2017
|
EDS on 05/12/2017
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
08/12/2017
|
EDS on additional information/clarification as sought by Regional Office
|
|
7
|
Nodal Officer
|
EDS
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
12/12/2017
|
The conditions to be complied
|
|
8
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
EDS
|
DFO (Territorial Division)
|
13/12/2017
|
Conditions as given by the Regional Office should be complied
|
|
9
|
DFO (Territorial Division)
|
EDS
|
User Agency (umehta89@gmail.com)
|
13/12/2017
|
The conditions 01, 03, 05 and 06 should be complied as per the directions received from the Regional office
|
|
10
|
User Agency (umehta89@gmail.com)
|
REPLY
|
DFO (Territorial Division)
|
14/12/2017
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Territorial Division)
|
REPLY
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
18/12/2017
|
A copy of the letter mentioning the compliance of the conditions is enclosed for kind perusal and necessary action.
|
|
12
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
REPLY
|
Nodal Officer
|
20/12/2017
|
The details of the compliance received from User Agency and as compiled by DCF is to be forwarded to the Regional Office, Bhopal for grant of Stage I Clearance.
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
10/01/2018
|
The conditions are complied and submitted for forwarding to the Regional Office
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
10/01/2018
|
The conditions complied by the User Agency and the DCF has been updated by the Nodal Officer. Necessary permission may be accorded for this specific case
|
|