TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/TRANS/23475/2017              (ii). Name of Project for which Forest Land is required : 220 KV DCDS Jagdalpur - Barsoor Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The power supply of whole Bastar Division comprising of seven revenue district namely Bastar,Bijapur,Dantewada,kanker,kondagaon,narayapur & Sukma are Taken by 220/132 KV Barsoor S/S Located in Dantewada District, for which 220KV feeders coming from Bhilai. The length of 220KV feeders are more than 2              (iv). File no. : FC-III/CH-25/2018-NGP              (v). State : Chhattisgarh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 70.782
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/CG/TRANS/23475/201703/06/201708/06/2017   20/06/2017   22/06/2017   23/06/2017

Dantewada :12/07/2017


Bastar :12/07/2017

Jagdalpur:
  13/12/2017 (Bastar)

Jagdalpur:
  13/12/2017 (Dantewada)

Chhattisgarh:
21/12/2017
Chhattisgarh:
28/12/2017
Raipur:
06/02/2018
23/04/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Raipur) on:22/02/2018  
Replied by State Government(Chhattisgarh) on:13/03/2018  
Query raised by Regional Office (Raipur) on:27/03/2018  
Replied by State Government(Chhattisgarh) on:26/04/2018  
Query raised by State Government (Chhattisgarh) on:07/03/2018  
Replied by Nodal Officer (Chhattisgarh) on:13/03/2018  
Query raised by State Government (Chhattisgarh) on:26/04/2018  
Replied by Nodal Officer (Chhattisgarh) on:26/04/2018  
Query raised by Nodal Officer (Chhattisgarh) on:07/03/2018  
Replied by Circle(Jagdalpur) on:11/03/2018  
Query raised by Nodal Officer (Chhattisgarh) on:13/03/2018  
Replied by Circle(Jagdalpur) on:13/03/2018  
Query raised by Circle (Jagdalpur) on:15/12/2017  
Replied by DFO (Bastar) on:15/12/2017  
Query raised by Circle (Jagdalpur) on:15/12/2017  
Replied by DFO (Dantewada) on:15/12/2017  
Query raised by Circle (Jagdalpur) on:09/03/2018  
Replied by DFO (Bastar) on:10/03/2018  
Query raised by Circle (Jagdalpur) on:09/03/2018  
Replied by DFO (Dantewada) on:11/03/2018  
Query raised by DFO (Dantewada) on:15/12/2017  
Replied by UA on :15/12/2017  
Query raised by DFO (Bastar) on:10/03/2018  
Replied by UA on :10/03/2018  
Query raised by DFO (Dantewada) on:11/03/2018  
Replied by UA on :11/03/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .