Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Balrampur)
|
EDS
|
User Agency (eepwddnrganj@gmail.com)
|
27/01/2017
|
In the proposal submitted in 06 copies Divisional Forest office
|
|
2
|
User Agency (eepwddnrganj@gmail.com)
|
REPLY
|
DFO (Balrampur)
|
24/03/2017
|
The correction have been made as per the instruction received
|
|
3
|
CF (Surguja)
|
EDS
|
DFO (Balrampur)
|
01/04/2017
|
Pls. Recheck the attachments and Part II form. Correct and Resend immediatly
|
|
4
|
DFO (Balrampur)
|
REPLY
|
CF (Surguja)
|
03/04/2017
|
Speclfic Recommendation of the DFO
Reason -
The area proposed by the applicant institution is Minimal and there is no other option. Therefore, it is recommended to provide forest land under the prescribed conditions for wadafnagar bypass road.a
|
|