TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/Others/36479/2018              (ii). Name of Project for which Forest Land is required : LIC BRANCH OFFICE, DANTEWADA              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LIC Building Dantewada              (iv). State : Chhattisgarh              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.262
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/CG/Others/36479/201811/10/201826/07/2019  26/03/2019  22/10/2018   20/08/2019  29/06/2019  06/02/2019   03/09/2019   07/09/2019 Dantewada :07/09/2019Jagdalpur:
  20/01/2021 (Dantewada)

Chhattisgarh:
03/06/2022
Chhattisgarh:
18/06/2024
Raipur:
24/07/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Raipur) on:20/08/2024  
Query raised by State Government (Chhattisgarh) on:20/09/2024  
Query raised by Nodal Officer (Chhattisgarh) on:29/06/2022  
Replied by Circle(Jagdalpur) on:29/06/2022  
Query raised by Nodal Officer (Chhattisgarh) on:01/07/2022  
Replied by Circle(Jagdalpur) on:14/03/2024  
Query raised by Nodal Officer (Chhattisgarh) on:12/04/2024  
Replied by Circle(Jagdalpur) on:27/05/2024  
Query raised by Nodal Officer (Chhattisgarh) on:26/09/2024  
Replied by Circle() on:  
Query raised by Circle (Jagdalpur) on:11/02/2021  
Replied by DFO (Dantewada) on:26/05/2022  
Query raised by Circle (Jagdalpur) on:15/07/2022  
Replied by DFO (Dantewada) on:13/03/2024  
Query raised by Circle (Jagdalpur) on:18/04/2024  
Replied by DFO (Dantewada) on:15/05/2024  
Query raised by Circle (Jagdalpur) on:16/05/2024  
Replied by DFO (Dantewada) on:21/05/2024  
Query raised by Circle (Jagdalpur) on:14/01/2025  
Replied by DFO () on:  
Query raised by DFO (Dantewada) on:25/02/2020  
Replied by UA on :25/06/2020  
Query raised by DFO (Dantewada) on:12/02/2021  
Replied by UA on :25/05/2022  
Query raised by DFO (Dantewada) on:19/07/2022  
Replied by UA on :06/03/2024  
Query raised by DFO (Dantewada) on:26/04/2024  
Replied by UA on :09/05/2024  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .
Close(X)
Close(X)
Please wait ...