Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dantewada)
|
EDS
|
User Agency (bo_38c@licindia.com)
|
25/02/2020
|
NOC not submitted by user agency
|
|
2
|
User Agency (bo_38c@licindia.com)
|
REPLY
|
DFO (Dantewada)
|
25/06/2020
|
The correction have been made as per the instruction received
|
|
3
|
CF (Jagdalpur)
|
EDS
|
DFO (Dantewada)
|
11/02/2021
|
Proposal Incomplete
|
|
4
|
DFO (Dantewada)
|
EDS
|
User Agency (bo_38c@licindia.com)
|
12/02/2021
|
Proposal Incomplete
|
|
5
|
User Agency (bo_38c@licindia.com)
|
REPLY
|
DFO (Dantewada)
|
25/05/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Dantewada)
|
REPLY
|
CF (Jagdalpur)
|
26/05/2022
|
Add. Information in 11 Points
|
|
7
|
Nodal Officer
|
EDS
|
CF (Jagdalpur)
|
29/06/2022
|
SEE PDF FILE AND COMPLY
|
|
8
|
CF (Jagdalpur)
|
REPLY
|
Nodal Officer
|
29/06/2022
|
No data attached
|
|
9
|
Nodal Officer
|
EDS
|
CF (Jagdalpur)
|
01/07/2022
|
SEE PDF FILE AND COMPLY
|
|
10
|
CF (Jagdalpur)
|
EDS
|
DFO (Dantewada)
|
15/07/2022
|
Complete the proposal quickly by filling the errors.
|
|
11
|
DFO (Dantewada)
|
EDS
|
User Agency (bo_38c@licindia.com)
|
19/07/2022
|
Please Objection full fill send revised proposal .
|
|
12
|
User Agency (bo_38c@licindia.com)
|
REPLY
|
DFO (Dantewada)
|
06/03/2024
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Dantewada)
|
REPLY
|
CF (Jagdalpur)
|
13/03/2024
|
Complete the proposal Quickly by filling the errors.
|
|
14
|
CF (Jagdalpur)
|
REPLY
|
Nodal Officer
|
14/03/2024
|
revised Information letter.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Jagdalpur)
|
12/04/2024
|
Please see attachment
|
|
16
|
CF (Jagdalpur)
|
EDS
|
DFO (Dantewada)
|
18/04/2024
|
Additional Principal Chief Conservator of Forest Land Management should ensure that the objections raised on the points in the proposal are resolved and sent immediately.
|
|
17
|
DFO (Dantewada)
|
EDS
|
User Agency (bo_38c@licindia.com)
|
26/04/2024
|
Fill the following deficiencies in the above proposal and submit the proposal as soon as possible.
|
|
18
|
User Agency (bo_38c@licindia.com)
|
REPLY
|
DFO (Dantewada)
|
09/05/2024
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Dantewada)
|
REPLY
|
CF (Jagdalpur)
|
15/05/2024
|
The shortcomings of the above proposal are being removed and presented again.
|
|
20
|
CF (Jagdalpur)
|
EDS
|
DFO (Dantewada)
|
16/05/2024
|
Incomplete Proposal
|
|
21
|
DFO (Dantewada)
|
REPLY
|
CF (Jagdalpur)
|
21/05/2024
|
The shortcomings of the above proposal are being removed and presented again.
|
|
22
|
CF (Jagdalpur)
|
REPLY
|
Nodal Officer
|
27/05/2024
|
Revised proposal submitted.
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
20/08/2024
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
20/09/2024
|
EDS
|
|
25
|
Nodal Officer
|
EDS
|
CF (Jagdalpur)
|
26/09/2024
|
SEE PDF FILE AND COMPLY
|
|
26
|
CF (Jagdalpur)
|
EDS
|
DFO (Dantewada)
|
14/01/2025
|
Moef rejected the proposal.
|
|