TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/Others/21373/2016              (ii). Name of Project for which Forest Land is required : RELIANCE JIO 4G PROJECT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : OFC Laying on Batati to Hati route in Korba District.              (iv). File no. : F-5-69/2017/10-2              (v). State : Chhattisgarh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.427
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/CG/Others/21373/201616/09/201617/09/2016   12/10/2016   28/10/2016   04/11/2016 Korba :09/11/2016Bilaspur(CG):
  11/04/2017 (Korba)

Chhattisgarh:
24/04/2017
Chhattisgarh:
29/09/2017
04/01/2018
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Chhattisgarh) on:11/07/2017  
Replied by Circle(Bilaspur(CG)) on:31/08/2017  
Query raised by Circle (Bilaspur(CG)) on:25/07/2017  
Replied by DFO (Korba) on:29/08/2017  
NOTE:- Stage-I Approval accorded by : State Government .