Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
03/10/2016
|
FRA certificate not uploaded in complete case please send immediately
|
|
2
|
DFO (Bastar)
|
EDS
|
User Agency (400kv.csptcl.jdp@gmail.com)
|
05/10/2016
|
FRA certificate Form -II and Subsection level committee report verified.
|
|
3
|
User Agency (400kv.csptcl.jdp@gmail.com)
|
REPLY
|
DFO (Bastar)
|
19/10/2016
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
21/10/2016
|
FRA Certificate and all documents submitted
|
|