TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/CG/Others/16723/2015
(ii). Name of Project for which Forest Land is required :
RELIANCE JIO 4G PROJECT
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Laying OFC Cable from Charama to Dhundrapal in kanker division
(iv). File no. :
F-5-03/2018/10-2
(v). State :
Chhattisgarh
(vi). Category of the Project :
Others
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.313
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Stage-I Approval on
Stage-II Approval on
FP/CG/Others/16723/2015
27/11/2015
17/09/2016
28/11/2015
12/10/2016
26/08/2016
31/10/2016
04/11/2016
Kanker
:
09/11/2016
Kanker
:
14/07/2017 (
Kanker
)
Chhattisgarh
:
21/09/2017
Chhattisgarh
:
26/12/2017
24/02/2018
By :State Government
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by Nodal Officer (Chhattisgarh) on:
14/11/2017
Replied by Circle(Kanker) on:
21/12/2017
NOTE:-
Stage-I Approval accorded by :
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
Nodal Officer
EDS
CF (Kanker)
14/11/2017
see pdf file and comply
2
CF (Kanker)
REPLY
Nodal Officer
21/12/2017
Problem shorted
EDS History(Stage-II)
×