TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/OFC/45529/2020              (ii). Name of Project for which Forest Land is required : BharatNet Project Phase-II Bijapur Forest Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : BharatNet project which is a GOI initiative. Under this project, connectivity will be provided at 5,987 GPs & 85 Blocks through optic fibre cable laying of approximately 32,466 KM. The laying of Optical Fiber cable of 32,466 KM will involve 26 districts across the State.              (iv). File no. : F 5-14/2021/10-2              (v). State : Chhattisgarh              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.706
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/CG/OFC/45529/202012/08/202025/08/2020   03/10/2020   22/10/2020   26/10/2020 Bijapur :27/10/2020Jagdalpur:
  08/02/2021 (Bijapur)

Chhattisgarh:
11/02/2021
Chhattisgarh:
18/02/2021
26/03/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Jagdalpur) on:11/02/2021  
Replied by DFO (Bijapur) on:11/02/2021  
NOTE:- Stage-I Approval accorded by : State Government .