TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/OFC/45138/2020              (ii). Name of Project for which Forest Land is required : BharatNet Project Phase-II Dharamjaygarh Forest Divission              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Land required for Optical Fibre Cable Laying works under National Optical Fibre Network Project of Bharat Broadband Network Limited (BBNL) for providing Broadband Connectivity of Blocks to Gram Panchayats.Optical Fibre Cable Laying from Dharamjaygarh and Lailunga Block Headquarter to Gram Pan              (iv). File no. : F 5-13/2021/10-2              (v). State : Chhattisgarh              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 17.329
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/CG/OFC/45138/202016/07/2020aa19/08/2020   03/09/2020 Dharamjaigarh :16/09/2020Bilaspur(CG):
  29/01/2021 (Dharamjaigarh)

Chhattisgarh:
08/02/2021
Chhattisgarh:
16/02/2021
17/03/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Dharamjaigarh) on:14/12/2020  
Replied by UA on :28/01/2021  
NOTE:- Stage-I Approval accorded by : State Government .