Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
11/06/2020
|
Proposal not completed
|
|
2
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
15/06/2020
|
L.No
|
|
3
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
15/06/2020
|
proposal not completed return proposal
|
|
4
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
19/06/2020
|
submitted
|
|
5
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
19/06/2020
|
submitted
|
|
6
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
19/06/2020
|
submitted
|
|
7
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
22/06/2020
|
latter
|
|
8
|
Nodal Officer
|
EDS
|
CF (Jagdalpur)
|
16/07/2020
|
SEE PDF FILE AND COMPLY
|
|
9
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
27/07/2020
|
Revised Proposal Apccf LM latter no. 1403 date 16-07-2020 and Ccf jagdalpur Circle latter no 3972 date 17-07-2020
|
|
10
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
25/08/2020
|
L.No. 1039 Date 18-08-2020
|
|
11
|
CF (Jagdalpur)
|
EDS
|
DFO (Bastar)
|
01/09/2020
|
Upload Inspection report.
|
|
12
|
DFO (Bastar)
|
REPLY
|
CF (Jagdalpur)
|
01/09/2020
|
Upload Inspection.
|
|
13
|
CF (Jagdalpur)
|
REPLY
|
Nodal Officer
|
01/09/2020
|
Reacquired documents uploaded.
|
|