TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/MIN/149564/2021              (ii). Name of Project for which Forest Land is required : Bhaskarpara Coal Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Bhaskarpara Coal Mine is allocated to M/s Prakash Industries Limited by Ministry of Coal, Government of India vide vesting order no.NA/104/5/2021-NA Dated 18.11.2021 for commercial coal mining.              (iv). File no. : 8-09/2023-FC              (v). State : Chhattisgarh              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 515.581
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/CG/MIN/149564/202126/11/202102/12/2021   02/03/2022   07/03/2022   08/03/2022 Surajpur :08/03/2022Surguja:
  05/12/2022 (Surajpur)

Chhattisgarh:
03/01/2023
Chhattisgarh:
05/01/2023
13/03/202321/08/2023
By :Head Office
Chhattisgarh
14/03/2024
11/07/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 29/03/2023  
Replied by State Government (Chhattisgarh) on:09/05/2023  
Query raised by State Government (Chhattisgarh) on:05/04/2023  
Replied by Nodal Officer (Chhattisgarh) on:01/05/2023  
Query raised by Nodal Officer (Chhattisgarh) on:05/04/2023  
Replied by Circle(Surguja) on:28/04/2023  
Query raised by Circle (Surguja) on:13/12/2022  
Replied by DFO (Surajpur) on:26/12/2022  
Query raised by Circle (Surguja) on:06/04/2023  
Replied by DFO (Surajpur) on:25/04/2023  
Query raised by DFO (Surajpur) on:13/06/2022  
Replied by UA on :27/11/2022  
Query raised by DFO (Surajpur) on:16/12/2022  
Replied by UA on :21/12/2022  
Query raised by DFO (Surajpur) on:06/04/2023  
Replied by UA on :08/04/2023  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 27/03/2024  
Replied by State Government (Chhattisgarh) on:13/05/2024  
Query raised by MoEFCC,New Delhi 28/05/2024  
Replied by State Government (Chhattisgarh) on:05/06/2024  
NOTE:- Stage-II Approval accorded by : Head Office .