TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/MIN/13199/2015              (ii). Name of Project for which Forest Land is required : GEVRA OPENCAST              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 112.385 Ha of Revenue Forest Land for Coal Mining.              (iv). File no. : 8-41/2017-FC              (v). State : Chhattisgarh              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 112.385
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/CG/MIN/13199/201511/06/201503/08/2015  18/07/2015  12/06/2015   06/08/2015  21/07/2015  19/06/2015   08/07/2015   09/07/2015 Katghora :25/08/2015Bilaspur(CG):
  26/02/2016 (Katghora)

Chhattisgarh:
15/10/2016
Chhattisgarh:
09/02/2017
29/04/201728/07/2017
16/08/2017
27/09/2017
By :Head Office
Chhattisgarh
16/12/2020
21/06/2022
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Nodal Officer (Chhattisgarh) on:09/11/2016  
Replied by Circle(Bilaspur(CG)) on:14/12/2016  
Query raised by Circle (Bilaspur(CG)) on:15/03/2016  
Replied by DFO (Katghora) on:03/06/2016  
Query raised by Circle (Bilaspur(CG)) on:23/06/2016  
Replied by DFO (Katghora) on:01/10/2016  
Query raised by Circle (Bilaspur(CG)) on:03/10/2016  
Replied by DFO (Katghora) on:07/10/2016  
Query raised by Circle (Bilaspur(CG)) on:16/11/2016  
Replied by DFO (Katghora) on:06/12/2016  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 22/01/2021  
Replied by State Government (Chhattisgarh) on:31/08/2021  
Query raised by MoEFCC,New Delhi 22/09/2021  
Replied by State Government (Chhattisgarh) on:04/01/2022  
Query raised by MoEFCC,New Delhi 29/01/2022  
Replied by State Government (Chhattisgarh) on:11/04/2022  
Query raised by State Government (Chhattisgarh) on:06/07/2021  
Replied by Nodal Officer (Chhattisgarh) on:11/08/2021  
Query raised by State Government (Chhattisgarh) on:13/10/2021  
Replied by Nodal Officer (Chhattisgarh) on:20/12/2021  
Query raised by Nodal Officer on:15/07/2021  
Replied by UA on :06/08/2021  
Query raised by Nodal Officer on:25/10/2021  
Replied by UA on :10/11/2021  
NOTE:- Stage-II Approval accorded by : Head Office .