  (i). Proposal No. : FP/BR/VELEC/37236/2018              (ii). Name of Project for which Forest Land is required : Village electrification under Deen Dayal Upadhyay Grameen Vidhyuthikaran Yojana              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Project taken under DDUGVY-11th Plan for village Electrification work for providing electricity to Fifteen thousand two hunderden thirteen (15213) rural households spread in 52 Villages and public places like Government Offices,health centers, Banks across the Nauhatta,Rohtas blocks of Rohtas Dist              (iv). State : Bihar              (v). Category of the Project : Village Electricity              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 4.941
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/VELEC/37236/201830/11/201829/09/2020   18/12/2018   29/09/2020 Rohtash :29/09/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Rohtash) on:29/09/2020  
Replied by UA on :30/09/2020  
Query raised by DFO (Rohtash) on:06/06/2022  
Replied by UA on :30/09/2020  
Query raised by DFO (Rohtash) on:02/02/2025  
Replied by UA on :20/10/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .