TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/BR/TRANS/39474/2019              (ii). Name of Project for which Forest Land is required : 132KV DC Dumraon(new)-Dumraon TL Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project is a part of TW02 Phase IV Part-II for the Bihar State transmission system strengthning and development program. With the completion of this project the power availability reliability and quality improve significantly in Buxar district and nearby areas.              (iv). File no. : Van Bhumi 139/ 2020              (v). State : Bihar              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.3755
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/BR/TRANS/39474/201922/03/2019aa11/04/2019   29/12/2020 Bhojpur :29/12/2020Patna:
  29/12/2020 (Bhojpur)

Bihar:
29/12/2020
Bihar:
29/12/2020
21/01/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)