  (i). Proposal No. : FP/BR/TRANS/38588/2019              (ii). Name of Project for which Forest Land is required : The construction of 33 KV line from Ram Chandrapur PSS to Meghi-Nagwan PSS is proposed under IPDS Scheme for which the section of the line from Ramchandrapur PSS to Makanpur is Coming under forest Are              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The construction of 33 KV line from Ram Chandrapur PSS to Meghi-Nagwan PSS is proposed under IPDS Scheme for which the section of the line from Ramchandrapur PSS to Makanpur is Coming under forest Are              (iv). File no. : FC-18/2019              (v). State : Bihar              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.3925
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/BR/TRANS/38588/201928/01/201917/05/2019   17/05/2019   05/02/2019   17/05/2019 Nalanda :17/05/2019Patna:
  17/05/2019 (Nalanda)

Bihar:
17/05/2019
Bihar:
17/05/2019
20/05/2019
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .