TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/BR/ROAD/54736/2020
(ii). Name of Project for which Forest Land is required :
Rehabilitation and Up gradation of 2–lane with Paved Shoulders configuration of NH-133E from Bhagalpur to Baljhor Basti (Bihar & Jharkhand state border) In the state of Bihar on EPC mode.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The project road is a part of newly declared NH 133E (old SH-19), starts at the Km 4.000 and ends at Km 63.600 of NH-133E (old SH-19). The project road runs from Bhagalpur to Baljhor (Bihar & Jharkhand border). There is an overlapping length of 2.670 kms of NH-333A from Dhaka Mor to Bheda Mor (Exist
(iv). State :
Bihar
(v). Category of the Project :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Area of forest land proposed for diversion(in ha.):
46.5848
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/BR/ROAD/54736/2020
04/12/2020
11/12/2020
15/12/2020
17/12/2020
28/12/2020
Banka
:
29/01/2021
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Proposal is pending at
DFO
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×