TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/BR/ROAD/54736/2020              (ii). Name of Project for which Forest Land is required : Rehabilitation and Up gradation of 2–lane with Paved Shoulders configuration of NH-133E from Bhagalpur to Baljhor Basti (Bihar & Jharkhand state border) In the state of Bihar on EPC mode.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project road is a part of newly declared NH 133E (old SH-19), starts at the Km 4.000 and ends at Km 63.600 of NH-133E (old SH-19). The project road runs from Bhagalpur to Baljhor (Bihar & Jharkhand border). There is an overlapping length of 2.670 kms of NH-333A from Dhaka Mor to Bheda Mor (Exist              (iv). State : Bihar              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 46.5848
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/ROAD/54736/202004/12/202011/12/2020   15/12/2020   17/12/2020   28/12/2020 Banka :29/01/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at DFO .
Close(X)