Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
14/12/2020
|
please submit Revised area of proposed forest land
|
|
2
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
21/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
02/06/2021
|
Before processing of FC proposal, recommendation from SC of NBWL is required.
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
11/07/2022
|
Before processing of FC proposal, recommendation from SC of NBWL is required.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Gaya)
|
11/07/2022
|
Before processing of FC proposal, recommendation from SC of NBWL is required.
|
|
6
|
CF (Gaya)
|
EDS
|
DFO (Nawada)
|
18/04/2023
|
Before processing of FC proposal, recommendation from SC of NBWL is required.
|
|
7
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
18/04/2023
|
Before processing of FC proposal, recommendation from SC of NBWL is required.
|
|
8
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
20/04/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
22/08/2023
|
1. Area sought by forest dept is 10.368 ha but it is wrongly depicted in the kml file. Pls correct it.
2. Toposheet map is wrongly depicting WLS boundary. Pls correct it.
|
|
10
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
28/08/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
12/10/2023
|
.The list of trees to be cut/translocated has been prepared in 2019 .Onsite verifcation of list is not possible as marking is not clear on trees and due to gap of 4 years it is necessary to revisit the tree list so that it reflects current physical status of trees
|
|
12
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
23/12/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
12/01/2024
|
as requested by you , I am sending back for required correction.
|
|
14
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
13/01/2024
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Nawada)
|
REPLY
|
CF (Gaya)
|
15/01/2024
|
NBWL has recommended the project. Updated inspection report and CA schemes have been uploaded.
|
|
16
|
CF (Gaya)
|
REPLY
|
Nodal Officer
|
30/01/2024
|
NBWL has recommended the project. Wildlife clearance has been obtained.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
21/02/2024
|
EDS Reply letter has been uploaded.
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
21/02/2024
|
EDS Reply letter has been uploaded.
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
29/02/2024
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
20/05/2024
|
EDS
|
|
21
|
Nodal Officer
|
EDS
|
CF (Gaya)
|
20/05/2024
|
EDS
|
|
22
|
CF (Gaya)
|
EDS
|
DFO (Nawada)
|
20/05/2024
|
EDS
|
|
23
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
20/05/2024
|
EDS
|
|
24
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
27/05/2024
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
30/07/2024
|
Equivalent non forest land details has been required
|
|
26
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
26/09/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Nawada)
|
EDS
|
User Agency (patna@nhai.org)
|
02/10/2024
|
certificate from Govt level competent authority is required stating that suitable land for CA is not available.
|
|
28
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Nawada)
|
17/10/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Nawada)
|
REPLY
|
CF (Gaya)
|
21/10/2024
|
A query was raised regarding the provision of a certificate of unavailability of land from the competent authority, which was not submitted by the user agency. As per the instructions of the Secretary, Department of Environment, Forest & Climate Change during the video conference on October 18, 2024, the project may be recommended only after fulfilling the following conditions, in accordance with Gazette Notification No. G.S.R. 582 (E) dated 20.09.2024:
1.The user agency must obtain a certificate from the competent authority declaring the project as 'exceptional.'
2.The user agency is required to submit a certificate from the competent authority regarding the unavailability of land.
This project is recommended only on the condition of strict adherence to the above points.
|
|
30
|
CF (Gaya)
|
EDS
|
DFO (Nawada)
|
22/10/2024
|
EDS
|
|
31
|
DFO (Nawada)
|
REPLY
|
CF (Gaya)
|
22/10/2024
|
EDS has been rectified
|
|
32
|
CF (Gaya)
|
REPLY
|
Nodal Officer
|
23/10/2024
|
EDS has been rectified
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
23/10/2024
|
EDS Reply letter has been uploaded.
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
23/10/2024
|
EDS Reply letter has been uploaded.
|
|