TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/BR/ROAD/25317/2017
(ii). Name of Project for which Forest Land is required :
Reliance Jio Infocomm Limited
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Reliance Jio Infocomm Limited is registered with Department of Telecommunication (DoT) as Infrastructure Provider category (IP-I) vide it's registration certificate no. is 370 / 2011 dated 23rd June, 2011 to establish and maintain the assets such as Dark Fibres, Right of way, Duct space and Tower. T
(iv). File no. :
Van Bhumi 92/2021
(v). State :
Bihar
(vi). Category of the Project :
Road
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.27126
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Stage-I Approval on
Stage-II Approval on
FP/BR/ROAD/25317/2017
27/03/2017
21/04/2017
03/05/2017
11/05/2017
01/09/2017
Jamui
:
01/09/2017
Bhagalpur
:
12/02/2018 (
Jamui
)
Bihar
:
19/02/2018
Bihar
:
17/08/2021
08/03/2022
By :State Government
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by Nodal Officer (Bihar) on:
19/02/2018
Replied by Circle(Bhagalpur) on:
17/08/2021
NOTE:-
Stage-I Approval accorded by :
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
Nodal Officer
EDS
CF (Bhagalpur)
19/02/2018
FRA certificate not provided by User Agency
2
CF (Bhagalpur)
REPLY
Nodal Officer
17/08/2021
FRA 2006 Submitted DFO
EDS History(Stage-II)
×