  (i). Proposal No. : FP/BR/Approach/152066/2022              (ii). Name of Project for which Forest Land is required : The proposal for establishment of retail out-let dealership of M/s NX100 PACIFIC BIOFUEL PVT Ltd.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposal for establishment of retail out-let dealership of M/s NX100 PACIFIC BIOFUEL PVT Ltd. Location Gaya to Sherghati Road in Gaya District Bihar. The Road Side land of 187.50 Sq. Mts. is required only for the proposal to use as approach Road. So that the vehicle can reach to retail outlet an              (iv). File no. : FP/BR/Approach/152066/2022              (v). State : Bihar              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.015
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/Approach/152066/202207/02/202218/07/2023   18/07/2023   18/07/2023   18/07/2023 Gaya :18/07/2023Gaya:
  15/09/2023 (Gaya)

Bihar:
15/09/2023
Bihar:
18/09/2023
Ranchi:
13/02/2024
14/02/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:26/02/2024  
Replied by State Government(Bihar) on:01/11/2024  
Query raised by State Government (Bihar) on:01/11/2024  
Replied by Nodal Officer (Bihar) on:01/11/2024  
Query raised by Nodal Officer (Bihar) on:01/11/2024  
Replied by Circle(Gaya) on:01/11/2024  
Query raised by Circle (Gaya) on:01/11/2024  
Replied by DFO (Gaya) on:01/11/2024  
Query raised by DFO (Gaya) on:15/09/2023  
Replied by UA on :15/09/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .