TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/TRANS/30498/2017              (ii). Name of Project for which Forest Land is required : 132 KV S/C Transmission line from Salakati Grid S/S to APM (Jogighopa)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed transmission line is approximately 42.00 km and is passing the kokrajhar and bongaigaon district of Assam covering few areas of forest land under Nadangiri RF Part-1.              (iv). File no. : 3-AS-B-044/2021/GHY              (v). State : Assam              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.9413
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/TRANS/30498/201708/11/201827/11/2018   12/12/2018   21/12/2018   12/01/2019 Haltugaon :17/01/2019Western Assam Circle, Kokrajhar:
  30/01/2021 (Haltugaon)

Assam:
03/02/2021
Assam:
23/07/2021
Guwahati:
09/08/2021
26/05/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:07/09/2021  
Replied by State Government(Assam) on:05/09/2022  
Query raised by Regional Office (Guwahati) on:20/09/2022  
Replied by State Government(Assam) on:20/10/2022  
Query raised by Regional Office (Guwahati) on:10/11/2022  
Replied by State Government(Assam) on:04/05/2023  
Query raised by Nodal Officer (Assam) on:10/03/2021  
Replied by Circle(Western Assam Circle, Kokrajhar) on:21/06/2021  
Query raised by Circle (Western Assam Circle, Kokrajhar) on:19/03/2021  
Replied by DFO (Haltugaon) on:21/06/2021  
Query raised by DFO (Haltugaon) on:19/03/2021  
Replied by UA on :17/04/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .