TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/QRY/26989/2017              (ii). Name of Project for which Forest Land is required : TOKRABANDHA HILL STONE QUARRY NO. 9              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For various development works of State of Assam as well as Central Govt. of India. Tokrabandha Hill Stone Quarry No. 9 located within Tokrabandha Hill P.R.F under Dhubri Division, Dhubri.              (iv). State : Assam              (v). Category of the Project : Quarrying              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/QRY/26989/201707/07/201710/08/2017  10/07/2017   12/08/2017  06/08/2017   08/08/2017   09/08/2017 Dhubri :14/08/2017C.F Lower Assam Social Forestry Circle, Bongaigaon:
  17/08/2017 (Dhubri)

Assam:
21/08/2017
Assam:
21/08/2017
Guwahati:
24/08/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:24/08/2017  
Replied by State Government(Assam) on:24/08/2017  
Query raised by Regional Office (Guwahati) on:08/05/2018  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .
Close(X)
Close(X)
Please wait ...