Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (C.F N.A.C, Tezpur)
|
EDS
|
DFO (Nagaon)
|
06/09/2022
|
Hard copies not submitted
|
|
2
|
DFO (Nagaon)
|
EDS
|
User Agency (imdadalighy@gmail.com)
|
12/09/2022
|
Submitted This Office Letter No. FNGT/A/74-Part-I/Lankaijuri Stone Mahal/2022/2903-05, dtd.05/09/2022
|
|
3
|
User Agency (imdadalighy@gmail.com)
|
REPLY
|
DFO (Nagaon)
|
12/09/2022
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Nagaon)
|
REPLY
|
CF (C.F N.A.C, Tezpur)
|
12/09/2022
|
This Office Letter No.FNGT/A/74(Part-I)/Lankaijuri Stone Mahal/2022/2903-05, dtd.05/09/2022
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
07/12/2022
|
Details sought
|
|
6
|
State secretary
|
REPLY
|
Regional Office
|
19/06/2023
|
Information submitted
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
17/07/2023
|
Details sought
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
17/07/2023
|
Documents uploaded
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
07/08/2023
|
Details sought
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
20/12/2023
|
Uploaded and submitted for kind information and necessary action
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
28/02/2025
|
Proposal now dealt by Ministry being mining category. Further correspondence may be forwarded to Ministry New Delhi as per New Adhiniyam
|
|