TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/QRY/153044/2022              (ii). Name of Project for which Forest Land is required : BELDENGA STONE MAHAL              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Nagaon district and other neighboring district of Assam has a huge shortage of quality stone for construction activities. The proposal for seeking operation of stone mahal of 5.12 Ha. area namely BELDENGA STONE MAHAL inside the Doboka RF under Nagaon Forest Division will enable to cater the hug              (iv). State : Assam              (v). Category of the Project : Quarrying              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 5.12
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/QRY/153044/202202/03/202208/03/2022   06/05/2022   10/05/2022   26/06/2022 Nagaon :28/06/2022C.F N.A.C, Tezpur:
  20/07/2022 (Nagaon)

Assam:
01/08/2022
Assam:
07/09/2022
Guwahati:
19/12/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:03/01/2023  
Replied by State Government(Assam) on:28/06/2023  
Query raised by Regional Office (Guwahati) on:17/07/2023  
Replied by State Government(Assam) on:17/07/2023  
Query raised by Regional Office (Guwahati) on:07/08/2023  
Replied by State Government(Assam) on:19/08/2023  
Query raised by Regional Office (Guwahati) on:15/09/2023  
Replied by State Government(Assam) on:02/11/2023  
Query raised by Regional Office (Guwahati) on:22/11/2023  
Replied by State Government(Assam) on:22/12/2023  
Query raised by Regional Office (Guwahati) on:28/02/2025  
Query raised by State Government (Assam) on:20/06/2025  
Query raised by Nodal Officer (Assam) on:24/06/2025  
Replied by Circle(C.F N.A.C, Tezpur) on:25/03/2026  
Query raised by Circle (C.F N.A.C, Tezpur) on:27/06/2025  
Replied by DFO (Nagaon) on:17/03/2026  
Query raised by DFO (Nagaon) on:16/08/2025  
Replied by UA on :07/11/2025  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .