Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Karimganj )
|
EDS
|
User Agency (anurag.sarma@ril.com)
|
21/02/2022
|
Resubmission of the proposal for diversion of Forest land by selecting suitable location for setting up of Mobile Tower as the present proposed location is found not fit by the User Agency.
|
|
2
|
User Agency (anurag.sarma@ril.com)
|
REPLY
|
DFO (Karimganj )
|
11/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (C.F Southern Assam Circle, Silchar)
|
EDS
|
DFO (Karimganj )
|
25/04/2022
|
Item No.4-II have to be corrected and re-submit the proposal.
|
|
4
|
DFO (Karimganj )
|
REPLY
|
CF (C.F Southern Assam Circle, Silchar)
|
25/04/2022
|
In item Sl. No.4(ii), the Scientific name of tree recorded as Abies Alba through oversight which is corrected as Aquillaria malaccensis.
|
|