TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/MIN/35965/2018              (ii). Name of Project for which Forest Land is required : To drill well Nos KSDB and KSDC from existing location of KSAB              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To drill well Nos KSDB and KSDC from existing location of KSAB. No extra Land is required and forest clearance of existing land is available. Both the wells will be drilled as gas injector wells.              (iv). State : Assam              (v). Category of the Project : Mining              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.8
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/AS/MIN/35965/201815/09/201806/01/2019  12/12/2018  28/09/2018   15/02/2019  27/12/2018  02/12/2018   12/03/2019   06/05/2019 Golaghat :09/05/2019C.F. E.A.C, Jorhat:
  29/08/2019 (Golaghat)

Assam:
03/09/2019
Assam:
20/02/2020
Guwahati:
20/07/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:02/08/2022  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .
Close(X)