TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/HYD/8294/2014              (ii). Name of Project for which Forest Land is required : Lower Kopili Hydro Electric Project (120 MW)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : It is a hydro electric project situated in the Dima Hasao and Karbi Anglong districts of Assam with installed capacity of 120 MW.              (iv). File no. : 8-53/2018-FC              (v). State : Assam              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 523.046
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/AS/HYD/8294/201427/11/201410/11/2017  19/09/2017  07/08/2017  12/06/2017  02/05/2017  24/12/2015  09/11/2015  06/12/2014   13/11/2017  01/11/2017  08/09/2017  29/07/2017  31/05/2017  19/04/2017  18/12/2015  31/10/2015   20/11/2017   04/12/2017

Dima Hasao Forest West Division, Haflong :06/12/2017


Hamren :06/12/2017

Karbi Anglong Circle(council) Diphu:
  02/04/2018 (Hamren)

Dima Hasao Circle(council) Haflong:
  10/04/2018 (Dima Hasao Forest West Division, Haflong)

Assam:
21/04/2018
Assam:
26/04/2018
01/06/201809/08/2018
16/10/2018
05/02/2019
By :Head Office
Assam
14/09/2020
04/12/2020
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 30/11/2018  
Replied by State Government (Assam) on:02/01/2019  
Query raised by Circle (Dima Hasao Circle(council) Haflong) on:13/04/2018  
Replied by DFO (Dima Hasao Forest West Division, Haflong) on:17/04/2018  
Query raised by Circle (Karbi Anglong Circle(council) Diphu) on:17/04/2018  
Replied by DFO (Hamren) on:17/04/2018  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 03/11/2020  
Replied by State Government (Assam) on:08/12/2020  
NOTE:- Stage-II Approval accorded by : Head Office .