| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Anjaw Forest Division)
|
EDS
|
User Agency (nazish1444bcc@gmail.com)
|
12/12/2022
|
Correction of Component wise Breakup in Part-I of Form A
|
|
|
2
|
User Agency (nazish1444bcc@gmail.com)
|
REPLY
|
DFO (Anjaw Forest Division)
|
09/03/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
03/06/2025
|
Details sought
|
|
|
4
|
State secretary
|
REPLY
|
Regional Office
|
03/09/2025
|
EDS reply
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
10/09/2025
|
With reference to State Govt letter No. FOR.3-268/Cons/2024/3743-46 dated 02.09.2025 of Govt. of Arunachal Pradesh above has been examined in this office and observed the following incomplete information:
(i)The corrected Kml file of the proposed area indicating the components involved as the
submitted kml file is only for muck area (1.212 ha) and Camp Area ( 0.708 ha ) without
the bridge area.
(ii) The KML/shape file of the identified CA site as not found not in the attached CD.
State Govt. is requested to furnish the above information to this office at the earliest for
further processing of the proposal.
State Government is requested to provide the information/details to this office at the earliest so that this proposal may be taken up in the coming REC
|
|
|
6
|
State secretary
|
REPLY
|
Regional Office
|
17/09/2025
|
EDS reply
|
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
08/10/2025
|
Details sought
|
|