| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Lohit Forest Division. Tezu)
|
EDS
|
User Agency (cemorth.itanagar@gmail.com)
|
21/09/2020
|
upload revised proposal.
|
|
|
2
|
User Agency (cemorth.itanagar@gmail.com)
|
REPLY
|
DFO (Lohit Forest Division. Tezu)
|
06/01/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
23/07/2021
|
Shortcoming
|
|
|
4
|
State secretary
|
REPLY
|
Regional Office
|
04/02/2022
|
Approval letter
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
11/02/2022
|
Details sought
|
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
23/11/2022
|
There is two project in same name
|
|