TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AR/ROAD/42951/2019              (ii). Name of Project for which Forest Land is required : Construction of Foot tracks for ITBP from Basam - Thathi              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest area required for Basam - Thathi Construction of Foot Tracks for ITBP in state of Arunachal Pradesh              (iv). State : Arunachal Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 17.03
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AR/ROAD/42951/201913/12/201907/01/2020   23/01/2020   29/01/2020   09/02/2021 Dibang Forest Division :09/02/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Dibang Forest Division) on:18/02/2021  
Replied by UA on :08/03/2021  
NOTE:- Proposal is pending at DFO .