  (i). Proposal No. : FP/AR/ROAD/28950/2017              (ii). Name of Project for which Forest Land is required : PROPOSAL FOR DIVERSION OF ADDITIONAL MUCK DISPOSAL AREA 7.33 HA. FOR IMPROVEMENT/UP GRADATION OF TRANS ARUNACHAL HIGHWAY (NH-52 B) FROM PASIGHAT-PANGIN ROAD (KM 0.00 TO KM 20.000) TO NHDL SPECIFICATION PASIGHAT FOREST DIVISION IN EAST SIANG DISTRICT OF ARUNACHAL PRADESH.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : PROPOSAL FOR DIVERSION OF ADDITIONAL MUCK DISPOSAL AREA 7.33 HA. FOR IMPROVEMENT/UP GRADATION OF TRANS ARUNACHAL HIGHWAY (NH-52 B) FROM PASIGHAT-PANGIN ROAD (KM 0.00 TO KM 20.000) TO NHDL SPECIFICATION PASIGHAT FOREST DIVISION IN EAST SIANG DISTRICT OF ARUNACHAL PRADESH.              (iv). State : Arunachal Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 7.33
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AR/ROAD/28950/201705/09/201707/09/2017   08/09/2017   08/09/2017   22/09/2017 Pasighat Forest Division,Pasighat :11/10/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at DFO .