TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/AR/ROAD/21615/2016
(ii). Name of Project for which Forest Land is required :
Two Laning of Joram – Koloriang section of NH 713 from Km 20.000 to Km 51.000 in Lower Subansiri District of the state of Arunachal Pradesh on EPC mode.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Proposal for diversion of additional 16.729 ha forest land for two laning of Joram – Koloriang section of NH 713 from 20.000 to 51.000 in the district of Lower Subansiri.
(iv). State :
Arunachal Pradesh
(v). Category of the Project :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Area of forest land proposed for diversion(in ha.):
16.729
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/AR/ROAD/21615/2016
05/10/2016
04/11/2016
04/06/2017
19/06/2017
07/07/2017
Hapoli Forest Division, Ziro
:
28/09/2018
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Proposal is pending at
DFO
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×