Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
06/01/2021
|
The EE, PR, Paderu is requested to submit RoFR Form-I certificate to process Part-II proposals of the Narellabanda to Sagulu road.
|
|
2
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
28/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2021
|
Additional information sought
|
|
4
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
06/07/2021
|
Request to Submit CA Land Details
|
|
5
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
14/07/2021
|
The DFO Narsipatnam is requested to re-submit the proposals along with non-forest land identified by CA
|
|
6
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
14/07/2021
|
The Executive Engineer, PR Division, Paderu is requested to submit CA land details as called for by the Prl.CCF&HoFF, A.P., Guntur for further process.
|
|
7
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
22/01/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
15/02/2022
|
The Executive Engineer, PR PIU Division, Paderu is requested to submit the reports on each road proposal to concerned Divisional Forest Officers along with all necessary documents i.e. CA area soil/ site suitability certificate, authenticated DGPS map, kml file and Proceedings of the District Collector, Visakhapatnam in 6 sets in hard and soft copies to process the road proposals for further process.
|
|
9
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
18/02/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
18/02/2022
|
The report along with CA land details are submitted herewith for further process
|
|
11
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
22/02/2022
|
The DFO, Narsipatnam is requested to submit proposal along with revised CA scheme details
|
|
12
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
24/02/2022
|
The Part-II proposal along with revised CA Scheme is submitted herewith for further process.
|
|
13
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
24/02/2022
|
The DFO, Narsipatnam and CCF, Visakhapatnam recommended the proposal, along with CA
|
|
14
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
03/03/2022
|
Request to attend on shortcomings
|
|
15
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
03/03/2022
|
The DFO, Narsipatnam is requested to submit rectified proposals as per the shortcomings communicated by the Nodal Officer
|
|
16
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
04/03/2022
|
The shortcomings and proportionate CA scheme details are uploaded and requested for taking further process.
|
|
17
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
04/03/2022
|
As per the instructions issued by the Nodal Officer rectified proposals along with CA details are uploaded.
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
07/03/2022
|
Ca land details submitted
|
|