TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/41926/2019              (ii). Name of Project for which Forest Land is required : Formation and BT to the road including construction of culverts from Sapparla to Gollapalli in G.K.Veedhi Mandal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Road from Sapparla to Gollapalli              (iv). File no. : 4-APC158/2022-VIJ              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 6.53
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/ROAD/41926/201906/09/201930/11/2020  06/11/2020  23/03/2020  23/03/2020  06/02/2020  23/10/2019   30/12/2020  20/11/2020  28/10/2020  23/03/2020  26/02/2020  24/12/2019   30/12/2020   31/12/2020 Narasipatnam :31/12/2020Visakhapatnam:
  12/01/2021 (Narasipatnam)

Andhra Pradesh:
24/02/2022
Andhra Pradesh:
08/03/2022
Vijayawada:
20/04/2022
03/05/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Andhra Pradesh) on:03/03/2022  
Replied by Circle(Visakhapatnam) on:03/03/2022  
Query raised by Circle (Visakhapatnam) on:19/01/2021  
Replied by DFO (Narasipatnam) on:04/03/2021  
Query raised by Circle (Visakhapatnam) on:04/03/2021  
Replied by DFO (Narasipatnam) on:04/03/2021  
Query raised by Circle (Visakhapatnam) on:03/04/2021  
Replied by DFO (Narasipatnam) on:18/02/2022  
Query raised by Circle (Visakhapatnam) on:22/02/2022  
Replied by DFO (Narasipatnam) on:24/02/2022  
Query raised by Circle (Visakhapatnam) on:03/03/2022  
Replied by DFO (Narasipatnam) on:03/03/2022  
Query raised by Circle (Visakhapatnam) on:03/03/2022  
Replied by DFO (Narasipatnam) on:03/03/2022  
Query raised by DFO (Narasipatnam) on:25/01/2021  
Replied by UA on :01/03/2021  
Query raised by DFO (Narasipatnam) on:02/03/2021  
Replied by UA on :03/03/2021  
Query raised by DFO (Narasipatnam) on:09/04/2021  
Replied by UA on :22/01/2022  
Query raised by DFO (Narasipatnam) on:15/02/2022  
Replied by UA on :18/02/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .