| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (WL Chittoor East)
|
EDS
|
User Agency (chennaipiu@gmail.com)
|
04/05/2022
|
APFD – FCA – 1980 – Proposals for diversion of forest land for formation of road from Chennai – Chittoor – Thachur Section of NH716B in favour of PD, NHAI – PIU, Chennai – DGPS Survey data of the degraded forest land identified for CA submitted for verification and authentication – Authentication map communicated - Part – I proposals submitted by the User Agency – Regarding.
|
|
|
2
|
User Agency (chennaipiu@gmail.com)
|
REPLY
|
DFO (WL Chittoor East)
|
19/05/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
05/08/2022
|
As per attached EDS
|
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
17/08/2022
|
Additional information called for
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (WLM - Tirupathi)
|
24/08/2022
|
Additional Information Requested
|
|
|
6
|
CF (WLM - Tirupathi)
|
EDS
|
DFO (WL Chittoor East)
|
01/09/2022
|
Additional information requested to submit the DFO, Chittoor East
|
|
|
7
|
DFO (WL Chittoor East)
|
REPLY
|
CF (WLM - Tirupathi)
|
07/09/2022
|
APFD FCA 1980– Proposals for diversion of forest land for construction of six-lane road from Chennai-Chittoor-Thachur section of NH-716B in favour of PD, NHAI-PIU, Chennai – DGPS Survey data of the degraded Forest land identified for CA submitted for verification and authentication – Authentication maps communicated – Part-I proposals submitted by the User Agency – Part-II proposals submitted – Certain information called for by the GoI – Information submitted - Reg.
|
|
|
8
|
CF (WLM - Tirupathi)
|
REPLY
|
Nodal Officer
|
07/09/2022
|
Additional information submitted
|
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
13/09/2022
|
Additional Information Submitted.
|
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
19/09/2022
|
Additional Information Submitted.
|
|