| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
04/06/2019
|
The DFO, Narsipatnam has not submitted CA land details, CA schemes etc., for the diversion proposal. Hence returned.
|
|
|
2
|
DFO (Narasipatnam)
|
EDS
|
User Agency (ee_piu_vspm@ap.gov.in)
|
10/06/2019
|
The U/a is requested to submit CA land and RoFR certificate and Part-I proposals in full shape.
|
|
|
3
|
User Agency (ee_piu_vspm@ap.gov.in)
|
REPLY
|
DFO (Narasipatnam)
|
01/03/2021
|
The correction have been made as per the instruction received
|
|
|
4
|
DFO (Narasipatnam)
|
EDS
|
User Agency (ee_piu_vspm@ap.gov.in)
|
02/03/2021
|
The EE, PRI Division, Paderu has submitted only reply in EDS without submitting hard copies to this office. The U/a is requested to submit CA land and RoFR certificate and Part-I proposals in full shape.
|
|
|
5
|
User Agency (ee_piu_vspm@ap.gov.in)
|
REPLY
|
DFO (Narasipatnam)
|
03/03/2021
|
The correction have been made as per the instruction received
|
|
|
6
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
04/03/2021
|
CA undertaking is submitted for further process.
|
|
|
7
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
03/04/2021
|
The proposals is returned due to non receipt of hard copies of the Part-II proposals.
|
|
|
8
|
DFO (Narasipatnam)
|
EDS
|
User Agency (ee_piu_vspm@ap.gov.in)
|
09/04/2021
|
The CF, Visakhapatnam has raised the EDS due for want of CA land details and also the User agency not handed over the hard copies of the proposals to the CF office and also not returned to this office.
|
|
|
9
|
User Agency (ee_piu_vspm@ap.gov.in)
|
REPLY
|
DFO (Narasipatnam)
|
24/01/2022
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Narasipatnam)
|
EDS
|
User Agency (ee_piu_vspm@ap.gov.in)
|
15/02/2022
|
The Executive Engineer, PR PIU Division, Paderu is requested to submit the reports on each road proposal to concerned Divisional Forest Officers along with all necessary documents i.e. CA area soil/ site suitability certificate, authenticated DGPS map, kml file and Proceedings of the District Collector, Visakhapatnam in 6 sets in hard and soft copies to process the road proposals for further process.
|
|
|
11
|
User Agency (ee_piu_vspm@ap.gov.in)
|
REPLY
|
DFO (Narasipatnam)
|
18/02/2022
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
18/02/2022
|
The report along with CA land details submitted for further process.
|
|
|
13
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
22/02/2022
|
The DFO, Narsipatnam is requested to submit proposal along with revised CA scheme details
|
|
|
14
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
24/02/2022
|
The Part-II proposal along with revised CA scheme is submitted here with for further process.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
03/03/2022
|
Request to attend on shortcomings
|
|
|
16
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
03/03/2022
|
The DFO, Narsipatnam is requested to submit rectified proposals as per the shortcomings communicated by the Nodal Officer
|
|
|
17
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
03/03/2022
|
The shortcomings and proportionate CA scheme details are uploaded and requested for taking further process.
|
|
|
18
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
04/03/2022
|
As per the instructions issued by the Nodal Officer rectified proposals along with CA details are uploaded.
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
07/03/2022
|
Request to attend on shortcomings
|
|
|
20
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
07/03/2022
|
The DFO, Narsipatnam is requested to attend the shortcomings as requested by the Nodal Officer.
|
|
|
21
|
DFO (Narasipatnam)
|
EDS
|
User Agency (ee_piu_vspm@ap.gov.in)
|
07/03/2022
|
The Executive Engineer, PR PIU Division, Paderu is requested to attend the shortcomings as requested by the Nodal officer.
|
|
|
22
|
User Agency (ee_piu_vspm@ap.gov.in)
|
REPLY
|
DFO (Narasipatnam)
|
07/03/2022
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
07/03/2022
|
The User agency has attended the shortcomings as per the instructions and submitted for further process.
|
|
|
24
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
07/03/2022
|
As per the instructions issued by the Nodal Officer rectified proposals are uploaded as reported by the DFO, Narsipatnam.
|
|