TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/28781/2017              (ii). Name of Project for which Forest Land is required : Chennai - Chittoor - Bangalore Road NH-4 road is included in NHDP-IV to upgrading to 4-lane from TN/AP Boarder to AP/KA Boarder Km 133/600 to 216/975 in Chittoor District, AP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Chennai - Chittoor - Bangalore Road NH-4 road is included in NHDP-IV to upgrading to 4-lane from TN/AP Boarder to AP/KA Boarder Km 133/600 to 216/975 in Chittoor District, AP              (iv). File no. : 4-APC045/2017-CHN              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 23.23
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/ROAD/28781/201719/08/201724/08/2017   01/09/2017   01/09/2017   01/09/2017

WL Chittoor East :01/09/2017


Chittor West :01/09/2017

Ananthapur:
  03/09/2017 (Chittor West)

WLM - Tirupathi:
  07/09/2017 (WL Chittoor East)

Andhra Pradesh:
14/09/2017
Andhra Pradesh:
22/09/2017
Vijayawada:
26/09/2017
05/10/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : Regional Office .