TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/149544/2021              (ii). Name of Project for which Forest Land is required : Road from Gummakota to Galipadu              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of (2.73+0.07+0.10+0.73)=3.63 ha. land for Formation & BT to the road including construction of Culverts from Gummakota to Galipadu of Ananthagiri Mandal of Chippapalli RF, Rompilli Beat, Vizianagaram Range, Vizianagaram Division in favour of Executive Engineer, PIU Division, Paderu unde              (iv). File no. : 4-APB205/2023-VIJ              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.63
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/ROAD/149544/202123/11/2021aa30/11/2021   08/06/2022 Vizianagram :08/06/2022Visakhapatnam:
  31/01/2023 (Vizianagram)

Andhra Pradesh:
04/02/2023
Andhra Pradesh:
06/02/2023
Vijayawada:
07/03/2023
16/06/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Vijayawada) on:22/03/2023  
Replied by State Government(Andhra Pradesh) on:15/05/2023  
Query raised by State Government (Andhra Pradesh) on:28/03/2023  
Replied by Nodal Officer (Andhra Pradesh) on:20/04/2023  
Query raised by Nodal Officer (Andhra Pradesh) on:06/04/2023  
Replied by Circle(Visakhapatnam) on:19/04/2023  
Query raised by Circle (Visakhapatnam) on:10/04/2023  
Replied by DFO (Vizianagram) on:13/04/2023  
Query raised by Circle (Visakhapatnam) on:17/04/2023  
Replied by DFO (Vizianagram) on:18/04/2023  
Query raised by DFO (Vizianagram) on:09/06/2022  
Replied by UA on :09/06/2022  
Query raised by DFO (Vizianagram) on:07/07/2022  
Replied by UA on :12/07/2022  
Query raised by DFO (Vizianagram) on:06/09/2022  
Replied by UA on :20/01/2023  
Query raised by DFO (Vizianagram) on:10/04/2023  
Replied by UA on :13/04/2023  
Query raised by DFO (Vizianagram) on:18/04/2023  
Replied by UA on :18/04/2023  
Query raised by DFO (Vizianagram) on:18/04/2023  
Replied by UA on :18/04/2023  